NYC DEP says an Asbestos Project Monitor’s Report (ACP-15) must be submitted in ARTS within 21 days of project completion, including successful clearance air monitoring.
DEP also says the report must be based on an inspection performed after all final clean-up steps listed in 15 RCNY § 1-112(m) are complete. The project monitor preparing the report must be independent of the abatement contractor. DEP assigns responsibility for compliance with this subdivision to the building owner.
For field planning, keep the completion and successful clearance sequence clear in your records, and make sure the report is based on the post-cleanup inspection. The filing window is a NYC DEP requirement; do not apply it automatically to another jurisdiction or treat this summary as a project-specific determination.